HOUSE OF ASSEMBLY
PUBLIC WORKS COMMITTEE
ETHELTON RAILWAY STATION PLATFORMS
REPLACEMENT PROJECT (DIT)
Old Parliament House Chamber, Old Parliament House
Monday, 14 November 2022 at 10:05am
BY AUTHORITY OF THE HOUSE OF ASSEMBLY
OFFICIAL: Sensitive
WITNESSES
ROCHE, BRIAN, Acting Executive Director, Transport Project Delivery,
Department for Infrastructure and Transport .................................................................................. 1
WALTHAM, DAVID, Delivery Manager, Transport Project Delivery, Rail Projects,
Department for Infrastructure and Transport .................................................................................. 1
Monday, 14 November 2022 House of Assembly Page 1
PUBLIC WORKS COMMITTEE
OFFICIAL: Sensitive
MEMBERS:
Mr M.E.
Standing Committees
53rd Parliament
-
Due to the frequent failures of this main, and its
significance in maintaining service delivery to customers, replacement is required.
Standing Committees
52nd Parliament
-
The current design of the track has a replacement
cycle of between 20 and 30 years.
Standing Committees
51st Parliament
-
The current design of the track has a replacement
cycle of between 20 and 30 years.
Standing Committees
55th Parliament
-
HOUSE OF ASSEMBLY
PUBLIC WORKS COMMITTEE
CITY SOUTH TRAM LINE REPLACEMENT
Old Parliament House Chamber, Old Parliament House, Adelaide
Thursday, 28 February 2019 at 9:35am
BY AUTHORITY OF THE HOUSE OF ASSEMBLY
WITNESSES
PISANIELLO, VICTOR, Project Manager, City South Tram Line Replacement,
Department of Planning, Transport and Infrastructure ................................................................... 1
WHELAN, JON, Executive Director, Transport Project Delivery,
Department of Planning, Transport and Infrastructure ................................................................... 1
Thursday, 28 February 2019 House of Assembly Page 1
PUBLIC WORKS COMMITTEE
MEMBERS:
Mr D.
Standing Committees
55th Parliament
-
HOUSE OF ASSEMBLY
PUBLIC WORKS COMMITTEE
CITY SOUTH TRAM LINE REPLACEMENT
Old Parliament House Chamber, Old Parliament House, Adelaide
Thursday, 28 February 2019 at 9:35am
BY AUTHORITY OF THE HOUSE OF ASSEMBLY
WITNESSES
PISANIELLO, VICTOR, Project Manager, City South Tram Line Replacement,
Department of Planning, Transport and Infrastructure ................................................................... 1
WHELAN, JON, Executive Director, Transport Project Delivery,
Department of Planning, Transport and Infrastructure ................................................................... 1
Thursday, 28 February 2019 House of Assembly Page 1
PUBLIC WORKS COMMITTEE
MEMBERS:
Mr D.
Standing Committees
53rd Parliament
-
HOUSE OF ASSEMBLY
PUBLIC WORKS COMMITTEE
CITY SOUTH TRAM LINE REPLACEMENT
Old Parliament House Chamber, Old Parliament House, Adelaide
Thursday, 28 February 2019 at 9:35am
BY AUTHORITY OF THE HOUSE OF ASSEMBLY
WITNESSES
PISANIELLO, VICTOR, Project Manager, City South Tram Line Replacement,
Department of Planning, Transport and Infrastructure ................................................................... 1
WHELAN, JON, Executive Director, Transport Project Delivery,
Department of Planning, Transport and Infrastructure ................................................................... 1
Thursday, 28 February 2019 House of Assembly Page 1
PUBLIC WORKS COMMITTEE
MEMBERS:
Mr D.
Standing Committees
52nd Parliament
-
At present, the railway corridor is owned by TransAdelaide.
Standing Committees
56th Parliament (Current)
-
Due to the frequent failures of this main, and its
significance in maintaining service delivery to customers, replacement is required.